Contracts / Realisations
-
First Block synchronization at Jaworzno 2 january 2020
On December 31, 2019, the first synchronization of Supercritical Block 910 at the Jaworzno Power Plant with the National Power Network was carried out.
SEE MORE -
Completion of construction of new units at Opole Power Plant 10 october 2019
On 10 October, in the Opole Power Plant belonging PGE Górnictwo i Energetyka Konwencjonalna of the PGE Group, the ceremony of completing the construction of two ultramodern generating units No. 5 and 6 with a total capacity of 1800 MW took place.
SEE MORE -
910MW Unit - Jaworzno Power Plant, Poland 18 october 2018
-
Leaflet from Jaworzno 910MW Unit construction site 30 september 2018
910MW Unit monthly info.
SEE MORE -
Important milestone of the Opole project 14 july 2016
On 14 July 2016 Opole project was at its half way to the successful finish. Two supercritical units are delivered by RAFAKO/Mosotostal Warszwa/Polimex Mostostal consortium for PGE Górnictwo i Energetyka Konwencjonalna.
SEE MORE