OFFER
References
BYDGOSZCZ 2 CHP Plant
Zespół Elektrociepłowni Bydgoszcz
Bydgoszcz
Installed dust extraction equipment:
Heat or electricity power | Boiler number | Flue gas flow [m^3/h] | Guaranteed emission [mg/m^3] | Fuel | Start-up Year |
---|---|---|---|---|---|
166 MW | K3 | 309 000 | <50 | bituminous coal | 2010 |
Installed boilers:
Boiler Type | Qty | Capacity [t/h] /Output Power [MW] | Steam Temperature [oC] | Steam Pressure [MPa] | Fuel | Start-up Year |
---|---|---|---|---|---|---|
OP | 4 | 230 t/h | 540 | 13,5 | bituminous coal | 1971 - 1983 |
WP | 2 | 139,5 MW | 155 | 1,2 | bituminous coal | 1974 - 1978 |